dbsim — Deutsche Bahn Simulation

CI License: MIT

A headless, event-driven simulation of the German railway network, built as a research instrument for studying how delays propagate across a timetable, where capacity bottlenecks form, and which dispatching strategies best contain disruption. It is an analysis tool rather than a renderer or a game: the engine runs without a user interface and emits a recording, and visualisation reads that recording afterward.

The leading research question is delay propagation — given a primary delay, where does it spread, how far, and how does the choice of dispatching rule change the outcome.

Bildfahrplan of the Frankfurt–Hannover corridor

A Bildfahrplan (time–distance diagram) of one simulated service day on the Frankfurt–Hannover corridor — 159 trains over 313 km, generated with dbsim bildfahrplan. Each line is a train; the slope is its speed, and crossings are where trains pass or meet.

Design principles

  • Deterministic per seed. A run is a pure function of its inputs and a single random seed; the same pair reproduces byte-for-byte. All randomness is routed through one seeded generator, and run hashes are compared in the test suite.
  • Headless core, separate visualisation. The simulation has no live rendering or inter-process streaming. It produces a self-describing recording; diagrams and replays are derived from it.
  • Multi-scale. The network is modelled at three levels of resolution — macroscopic (national timetable), mesoscopic (track segments and contention), and microscopic (one curated zone, signal by signal).
  • Swappable dispatching. Conflict resolution is a pluggable interface, so competing strategies can be compared on identical instances.
  • Grounded in real data and theory. Timetables, live delays, and track geometry come from public feeds; the models follow established railway operations theory (blocking-time stairways, UIC 406 capacity, the alternative-graph dispatching model).

How it works

Execution model

The core is a discrete-event simulation. A single priority queue (heapq) of timestamped events advances the clock from one event to the next, rather than in fixed time steps, so the cost of a run scales with the number of events rather than with simulated duration. Every stochastic decision draws from one seeded generator (seed.py), with independent sub-streams derived by hashing a label into a child seed. This makes a run reproducible across processes and platforms.

Data layer

Static timetables come from the gtfs.de GTFS feeds and are normalised into a columnar DuckDB store. Live punctuality comes from the GTFS-RT TripUpdate feed. Infrastructure geometry — track counts, signals, and switches — is extracted from OpenStreetMap through the Overpass API. None of this data is committed to the repository; a small source.json manifest pins each download (see docs/data-versioning.md).

Macroscopic scale

The national timetable is compiled into a time-expanded graph in rustworkx: nodes are (station, time) events and edges are train runs and feasible transfers. Earliest-arrival journeys are shortest paths over this graph. Simulation drives each train through its scheduled stops; the delay model injects primary delays, recovers slack within dwell margins, and holds connecting services within configured transfer and maximum-wait limits. Propagation is strictly causal — a delay can never move an event earlier than its schedule. A full national service day simulates in a few seconds, which kept the engine in Python (see docs/performance-profile.md).

Against live data, simulated downstream delays correlate with observed delays (r ≈ 0.47 overall, higher on materially delayed trains), confirming the propagation model is calibrated rather than merely plausible (docs/validation-report.md).

Simulated vs observed downstream delay

Each point is one downstream stop on a nationwide service day (n ≈ 123,000): the model's simulated delay against the delay actually observed in the GTFS-RT feed. Mass concentrates along the diagonal, where the two agree.

Mesoscopic scale

Station-to-station segments are classified as single- or double-track by counting parallel ways across OpenStreetMap cross-sections. Each segment is then a capacity-constrained resource that trains acquire and release under a minimum-headway constraint derived from blocking-time theory; opposing movements on single track must therefore resolve their meet at a station. Oversubscription is detected as a conflict before dispatching, and a pluggable Dispatcher resolves the remaining contention. Capacity is quantified by UIC 406 blocking-time compression, yielding per-segment occupancy and the corridor bottleneck.

Microscopic scale

One zone — the Pfäffingen passing loop on the Ammertalbahn, chosen from a survey of OpenStreetMap coverage (docs/zone-survey.md) — is modelled to the individual signal and switch. Blocking-time stairways are computed from speed profiles via forward and backward passes over each route, giving the minimum headway between successive movements. Opposing trains are routed to a free loop track to avoid deadlock, and the zone's occupancy is coupled back into the macroscopic schedule at its boundary, so microscopic contention becomes macroscopic delay (docs/micro-validation.md).

Blocking-time stairway at the Pfäffingen loop

A blocking-time stairway for two successive trains over the Pfäffingen route. Each shaded band is the interval a block is exclusively reserved for a train; the diagonal line is the train's path. The minimum headway is the closest the second train (red) can follow without its bands overlapping the first (blue).

Dispatching and optimisation

Track contention is formalised as an alternative graph (Mascis & Pacciarelli): fixed arcs encode each train's route, and a disjunctive pair on every shared resource encodes the ordering decision. Three solvers operate on the same graph:

  • a priority rule, which always favours the higher-priority train;
  • the AMCC heuristic (Avoid Most Critical Completion), which selects orderings greedily while staying cycle-free;
  • a CP-SAT model (OR-Tools) that returns the minimum-makespan schedule.

The CP-SAT optimum is a lower bound against which the heuristic is measured, so the cost of using a fast heuristic instead of an exact solver can be quantified exactly.

Robustness analysis

A Monte Carlo harness calibrates a primary-delay model from the empirical GTFS-RT delay distribution — the probability a train starts late and a non-parametric bootstrap pool of how late — then runs N reproducible replications, each with an independent seed derived from a base seed. It reports the outcome distribution: delay percentiles across simulated days and the stations that most consistently accumulate delay (the network's fragile points). The same machinery drives the strategy comparison, evaluating the three dispatchers across a common ensemble of disruptions.

Installation

Requires uv and Python 3.12 or newer.

uv sync                      # create the virtual environment and install deps
uv run dbsim sim             # smoke test: a deterministic event-loop run hash
uv run pytest                # test suite, including the determinism harness
uv run ruff check .          # lint
uv run ruff format --check . # formatting
uv run mypy                  # static type checking

Usage

The tool is a single command, dbsim, with subcommands. Each accepts --help. The examples below assume a timetable has been ingested.

Timetable ingestion and queries

# Download a gtfs.de feed and load it into DuckDB.
# `fv` is the long-distance (ICE/IC) network; `free` is the full national feed.
uv run dbsim ingest --feed fv

# All trains calling at a station on a given date.
uv run dbsim query trains "Frankfurt(Main)Hbf" --date 20260616 \
    --db data/processed/gtfs-fv.duckdb

# The full scheduled stop sequence of a single trip.
uv run dbsim query trip 124021 --db data/processed/gtfs-fv.duckdb

Journey planning and the time–distance diagram

# Time-expanded graph statistics (event nodes/edges, stations, connectivity).
uv run dbsim graph --date 20260616 --db data/processed/gtfs-fv.duckdb

# Earliest-arrival journey, including transfers.
uv run dbsim route "Frankfurt(Main)Hbf" "München Hbf" \
    --date 20260616 --depart-after 08:00 --db data/processed/gtfs-fv.duckdb

# Bildfahrplan: the scheduled time–distance diagram for a corridor.
uv run dbsim bildfahrplan --date 20260616 \
    --db data/processed/gtfs-fv.duckdb --out viz/bildfahrplan.png

Macroscopic simulation and delay propagation

# Simulate a corridor (default) or the whole network (--all). Unperturbed, the
# simulation reproduces the published timetable exactly and deterministically.
uv run dbsim run --date 20260616 --db data/processed/gtfs-fv.duckdb
uv run dbsim run --date 20260616 --db data/processed/gtfs-fv.duckdb --all

# Inject a primary delay (TRIP:SEQ:SECONDS) and observe the cascade.
uv run dbsim run --date 20260616 --db data/processed/gtfs-fv.duckdb \
    --delay 124021:0:1200          # ICE 22, +20 min at Frankfurt

Recording and replay

# Emit a self-describing Parquet recording, then reconstruct positions from it.
uv run dbsim run --date 20260616 --db data/processed/gtfs-fv.duckdb --all \
    --record data/processed/run.parquet
uv run dbsim replay data/processed/run.parquet --at 08:00 \
    --db data/processed/gtfs-fv.duckdb

notebooks/replay.ipynb works through a replay end to end (activity curve, trajectories, and a map snapshot).

Validation against real-time data

# Capture a live snapshot, then compare the model against observed delays.
# Validation uses the full feed, since RT trip ids match `free`, not `fv`.
uv run dbsim rt-capture data/raw/gtfsrt/today --count 1
uv run dbsim ingest --feed free
uv run dbsim validate data/raw/gtfsrt/today/snapshot-*.pb \
    --feed data/raw/gtfs/gtfsde-free/<date>/feed.zip --date <YYYYMMDD> \
    --scatter viz/validation.png

Track-segment model and capacity

# Classify single- vs double-track per segment from OpenStreetMap.
uv run dbsim segments --db data/processed/gtfs-free.duckdb \
    --stations "Tübingen Hbf;Unterjesingen Mitte;Entringen;Herrenberg"

# Mesoscopic meet: opposing trains contend for single-track segments.
uv run dbsim meso --db data/processed/gtfs-free.duckdb \
    --stations "Tübingen Hbf;Unterjesingen Mitte;Entringen;Herrenberg"

# Dispatch a line closure: choose a policy, close a segment over a time window.
uv run dbsim meso --db data/processed/gtfs-free.duckdb \
    --stations "Tübingen Hbf;Unterjesingen Mitte;Entringen;Herrenberg" \
    --dispatcher priority --close 1:0:1800

# Run a declarative disruption scenario from a file.
uv run dbsim scenario scenarios/ammertal-closure.json \
    --db data/processed/gtfs-free.duckdb

# UIC 406 capacity utilisation per segment, with the bottleneck.
uv run dbsim capacity --db data/processed/gtfs-free.duckdb --date 20260616 \
    --stations "Tübingen Hbf;Unterjesingen Mitte;Entringen;Herrenberg"

Microscopic zone

# Opposing trains meet at the loop without deadlock.
uv run dbsim meet

# Embed the micro zone in the macroscopic schedule and propagate its contention.
uv run dbsim couple --date 20260616 --db data/processed/gtfs-free.duckdb

Dispatching: heuristic versus optimal

# Priority rule vs AMCC vs the CP-SAT optimum on a delayed meet.
uv run dbsim reschedule --delay 1000

# Optimal-vs-heuristic on a harder three-train instance, with the gap quantified.
uv run dbsim optimal

Monte Carlo robustness

# Calibrate the delay model from a GTFS-RT snapshot, then run N replications.
# Reports total-delay percentiles and the network's fragility hotspots.
uv run dbsim montecarlo --db data/processed/gtfs-fv.duckdb --date 20260616 \
    --reps 500 --snapshot data/raw/gtfsrt/<date>/snapshot-*.pb

# Without a snapshot, supply a manual model.
uv run dbsim montecarlo --db data/processed/gtfs-fv.duckdb --date 20260616 \
    --reps 200 --p-delayed 0.3 --mean-delay 300

Methodology and results: docs/robustness-study.md.

Strategy comparison

This compares all three dispatchers across a Monte Carlo ensemble of disruptions on a contended single-track corridor. It needs no downloaded data to run with a manual disruption model:

uv run dbsim study --reps 300 --p-delayed 0.4 --mean-delay 600
  strategy       mean      p50      p90      max   (clearance delay, min)
  priority       99.5    101.7    110.0    111.7
  amcc           38.1     38.3     45.0     51.7
  optimal        38.0     38.3     45.0     51.7

Each figure is the extra time, in minutes, needed to clear every train from the corridor relative to free running. Alternative-graph dispatching roughly halves that delay against the priority rule across the whole distribution, and the AMCC heuristic essentially matches the CP-SAT optimum. To calibrate the disruptions from real data instead, pass a snapshot:

uv run dbsim study --reps 1000 --snapshot data/raw/gtfsrt/<date>/snapshot-*.pb

The full write-up is docs/strategy-comparison-study.md.

Repository layout

src/dbsim/
├── seed.py        # central seed control (the single source of randomness)
├── engine/        # discrete-event loop, events, train movement
├── record/        # recording format and determinism hashing
├── ingest/        # GTFS, GTFS-RT, and OSM extraction
├── model/         # infrastructure and the timetable graph
├── dispatch/      # swappable dispatchers and the optimisation solvers
├── scenario/      # declarative disruption definitions
└── analysis/      # metrics, validation, capacity, robustness studies
data/              # raw and processed data (git-ignored)
docs/  viz/  notebooks/  tests/

License

MIT

About

Headless, event-driven simulation of the German railway (Deutsche Bahn) network — a research tool for studying delay propagation, capacity bottlenecks, and dispatching strategies across macroscopic, mesoscopic, and microscopic scales.

Topics

Resources

Stars

5 stars

Watchers

0 watching

Forks

Releases

Packages

Contributors

Languages