Notifications
You must be signed in to change notification settings - Fork 0
EMS setup
This example demonstrates how to setup up a Strandnet Energy Management System.
-
Create asset:
- Go to the
Assetspage and click the+icon - Select the
Strandnet Energy Optimisation Assetand name it (EMS) - Click
ADDto create the asset
- Go to the
-
Generate power limit profiles:
- Fill in the
Power limit maximum profile (kW)field (1000) - Click the
Generate power limit maximum profile manual inputcheckbox - Fill in the
Power limit minimum profile (kW)field (-1000) - Click the
Generate power limit minimum profile manual inputcheckbox
- Fill in the
This will create a power limit profile with 15-minute steps for each day of the week in the Power limit maximum profile manual input field. You can manually change values for each interval and click the submit arrow when you are done. You can also copy the text and save it as a .csv file. This CSV file you can open with a spreadsheet program like google sheets. In your spreadsheet you can make adjustments and export the new power profile again as a CSV file. Next, you can open this CSV file in a text editor and copy the text to the Power limit maximum profile manual input and submit the changes by clicking the submit arrow. You can do the same for the Power limit minimum profile manual input. You can also choose to only set a maximum or minimum power limit profile, it is not required to have both for the optimisation routine.
- Display power limit profiles:
- Go to the
Insightspage and click the+icon - Create a
Line Chartand name it (Power limit profiles) - Connect the
Power limit maximum profile manualandPower limit maximum profile manualattributes - Set the Display
Default timeframeto This day - Click
SAVEand thenVIEWto exit theMODIFYmode
- Go to the
Now you have a line chart with your power limit profiles. You can change the time range to see your power limit profile for different days or the whole week.
- Setup optimisation method:
- Connect your main meter power readout to the
Power net (kW)attribute - Select the
Optimisation methodStrandnet alpha from the dropdown menu - Create a
Strandnet electricity battery assetand name it (Batterij GEMS)
- Connect your main meter power readout to the
Note: If problems occur during power limit profile setup you can go the the Logs page to get information about the type of error.