Composes the four tools in the project-controls toolkit, EVM dashboard, schedule health, change control, and risk trend, against one consistent programme, and produces a single integrated status report showing how the four disciplines' independent findings relate to each other.
Part of a small project-controls toolkit: project-controls-dashboard, schedule-health-analyzer, change-control-register, risk-trend-tracker, project-controls-reporting-engine (this repo).
Each tool in the toolkit answers its own question well: is the cost/schedule picture healthy, is the schedule itself healthy, is the change log under control, is risk exposure improving. What none of them answers alone is whether those four answers are actually telling the same story. A programme can show a schedule slip, a cost variance, some approved changes, and a worsening risk in the same reporting period and still get presented as four unrelated line items in four separate meetings, when they're often one underlying problem seen from four angles.
- Import each tool's existing metrics module unchanged (vendored under
engines/, see Implementation) and run all four against one shared fictional programme instead of each tool's own separate demo scenario. - Print a consolidated status report: EVM headline, Schedule Health Score, change control summary, and Risk Trajectory Score, side by side.
- Add one "Integrated Observations" section that states, in plain language, what the four independent computations agree on, without introducing any new predictive or causal model. It's factual juxtaposition of real computed numbers, not a forecast of how one discipline's number causes another's.
The sample programme is a fictional LNG compressor station retrofit where a single root cause, a long-lead compressor rotor procurement delay, is traceable independently through all four tools: it drives the schedule's 30-day slip, shows up in the EVM cost variance from the resulting expedited freight, appears as the change register's largest approved cost item, and was already flagged as an escalating risk months before it happened.
Built in Python, and deliberately reuses rather than reimplements: the
engines/ folder holds the exact same metrics.py (and cpm.py) modules
already published in the four standalone tools, copied unchanged so this
repo is self-contained and runnable without cloning the other four
alongside it. No new EVM, CPM, change-tracking, or risk-scoring logic
exists anywhere in this repo, the only new code is the orchestration script
that calls all four, a small chart-style/formatting layer shared with the
other five repos, and the one unified dataset that feeds them consistently.
====================================================================
INTEGRATED PROGRAMME STATUS REPORT
Ridgeline LNG Compressor Station Retrofit — as of 2026-08-01
====================================================================
COST / EVM (dashboard engine)
SPI 0.85 CPI 0.91 EAC $2,637,363 VAC -$237,363
SPI-based forecast finish: 2026-09-10 Revised budget (BAC + approved changes): $2,457,000
SCHEDULE (schedule health engine)
Schedule Health Score: 38.3/100 Slip: +30d Critical/near-critical: 66.7%
CHANGE CONTROL (change engine)
Approved: $57,000 (-5d) Pending: $22,000 Stale pending: 0
RISK (risk trend engine)
Risk Trajectory Score: 83.3/100 Effective mitigations: 2/3
Exposure change: +0.0% (shared-risk basis for the score above; raw incl. register churn: +111.1%)
Followed by the Integrated Observations section connecting the four findings to the same root cause. A saved copy is generated alongside the chart: see assets/report.md.
Four disciplines, one programme — cost/EVM, current schedule by criticality, cumulative approved change cost, and portfolio risk exposure, all computed from the same underlying story.
- This is composition, not new analysis: every number here is produced by one of the four existing tools' unmodified logic. If a discipline's standalone tool has a limitation (see its own README), that limitation carries through here too.
- The "Integrated Observations" are a written, human-composed narrative connecting the four results, not an automated root-cause-detection algorithm. It doesn't scale to a programme where the four disciplines don't share an obvious common cause, that would need real correlation analysis, which this deliberately doesn't attempt.
- One unified dataset drives all four engines; a real deployment would need this fed from each tool's actual system of record (P6/MS Project, the cost/ERP system, the RAID log, the change register) rather than one set of hand-authored CSVs.
The hard part of this build wasn't writing new logic, there isn't any, it was designing one dataset that stays numerically honest across four different schemas at once: an aggregated monthly EVM timeseries, an activity-level CPM network, a change log, and a risk panel, all describing the same 30-day schedule slip and its downstream cost, change, and risk consequences without any of the four disagreeing with each other. That turned out to be a more realistic simulation of "does your data actually add up across your reporting" than anything in the four standalone tools, which is arguably the actual point of a reporting engine like this one.
pip install -r requirements.txt
python reporting_engine.pySwap in your own data/*.csv files (same schemas as the four standalone
tools, see their READMEs) describing one real programme to point this at
it. All four engines will run against whatever story the data actually
tells. The BAC/PROJECT_START/PLANNED_FINISH/STATUS_DATE constants
near the top of reporting_engine.py are this fictional programme's
assumptions too, not read from the CSVs, so update those by hand as well.