Companion code for the article 'Machine Allocation on a Production Line': a CP-SAT model for scheduling unrelated parallel machines with changeovers, release dates and maintenance, compared with dispatching rules in five simulated experiments.

Topics

Resources

Stars

0 stars

Watchers

0 watching

Forks

Repository files navigation

machine-allocation

CI Python License

Companion code for the article Machine Allocation on a Production Line.

A simulated plant with six unrelated parallel machines, machine eligibility, material release dates, sequence-dependent changeovers and planned maintenance; a CP-SAT model that minimises lateness penalties plus operating cost; three constructive rules to compare it with; and five experiments around it.

The reference week planned by the cost-aware greedy rule and by CP-SAT

The problem

Machines Six, in three age classes. Newer machines run faster and change over faster but cost more per hour (€95, €70 and €48).
Jobs Five product families. Not every machine can run every family.
Changeovers Asymmetric and sequence-dependent, family to family. The first job, and the first job after a stop, needs a cold start.
Time constraints Release dates when material arrives late, due dates, and priority weights of 1, 2 or 5.
Stops Planned maintenance on four machines. For rescheduling, unplanned breakdowns.
Objective A penalty per weighted hour late (€60 by default), plus running cost, plus €1 per changeover minute.
Run times Real times depart from nameplate rates by machine class, material grade and lot size, plus noise. Planners only see a historical log.

All data are simulated. The plant parameters are in src/machine_allocation/instance.py.

Installation

Python 3.11 or later.

git clone https://github.com/DiogoRibeiro7/machine-allocation.git
cd machine-allocation
python -m venv .venv
source .venv/bin/activate            # Windows: .venv\Scripts\activate
pip install -e ".[figures]"          # ".[dev]" adds the test and lint tools

Quick start

from machine_allocation.heuristics import best_baseline
from machine_allocation.instance import int_times, make_instance
from machine_allocation.model import solve
from machine_allocation.simulate import evaluate

inst = make_instance(n_jobs=20, horizon_h=48)       # simulated plant and order book
P = int_times(inst, inst.true_mean)                  # whole minutes per job and machine; -1 if ineligible
pen = 1.0                                            # EUR per weighted minute late
hint, rule = best_baseline(inst, P, pen)             # best of EDD, tuned ATCS and the greedy rule
res = solve(inst, P, time_limit=10, penalty_per_min=pen, hint_seqs=hint)

for name, plan in ((rule, hint), ("CP-SAT", res["seqs"])):
    ev = evaluate(inst, plan, P, pen)
    print(f"{name:7} €{ev['total']:,.0f}   {ev['weighted_tardiness_h']:.1f} weighted hours late")
EDD     €15,260   15.1 weighted hours late
CP-SAT  €13,100   0.5 weighted hours late

A plan is a dict machine -> sequence. A sequence lists job indices in the order they run, and a planned stop is written as -(k+1) for stop k of that machine. time_limit is in CP-SAT's deterministic work units, not seconds (see Reproducing).

Package

Module Contents
instance Plant and order-book generator
model CP-SAT model: optional intervals plus a circuit constraint per machine. Also covers rescheduling with frozen work and a cap on machine changes.
heuristics EDD list rule, tuned ATCS dispatching, cost-aware greedy
simulate Order-preserving execution and scoring
times Production log and the four processing-time estimators

Reproducing the article

pip install -e ".[figures]"
./run_all.sh                     # every experiment, into results/
python experiments/figures.py    # every figure, into figures/
Script Question Results Figures
exp1_reference_plan.py The reference week: three rules and the solver exp1_reference_plan.json, exp1_plans.pkl fig1_gantt, fig2_anytime
exp2_frontier.py Operating cost against lateness, by penalty (VOLUME=1.1 for the larger order book) exp2_frontier.json, exp2_frontier_v110.json fig3_frontier
exp3_run_times.py Plans built on five processing-time matrices, three solver seeds each, executed exp3_run_times.json fig4_run_times, fig5_slack
exp4_breakdown.py A machine fails mid-week: right-shift or re-optimise exp4_breakdown.json
exp5_scaling.py 20 to 120 jobs at a fixed solver budget exp5_scaling.json
exp5b_large_long.py The 120-job instance with six times the budget exp5b_large_long.json
exp6_load.py The same order book at different volumes exp6_load.json fig6_load

Experiment 1 must run first; the others only need its output. run_all.sh options:

  • QUICK=1 ./run_all.sh is a smoke test with tiny budgets. It writes to results_quick/, and QUICK=1 python experiments/figures.py then draws into figures_quick/. CI runs both.
  • FROM=exp3 ./run_all.sh skips the experiments listed before the first match.
  • PYTHON=python3.12 ./run_all.sh picks the interpreter.

Each experiment logs to results/<name>.log, and the script exits non-zero if any experiment failed. On Windows, run it from Git Bash.

The solver runs with four interleaved workers and a deterministic-time budget, so a run returns the same plans on any machine with the same OR-Tools version (9.15 here). Wall-clock time is machine-dependent: the full set is 49 solves and took just under three hours on two cores. exp3_run_times.py caches each finished solve in results/exp3_cache/ and can be interrupted and resumed; delete that folder to recompute.

Every solve runs in its own process (solve_isolated in model.py) and is retried if the process dies. That is not decoration: the native solver aborted twice with a memory fault while these results were being produced, and both times the retry returned the plan.

Development

pip install -e ".[dev]"
pre-commit install       # ruff and file hygiene on every commit
pytest                   # unit and integration tests
ruff check .
mypy

The tests pin down the properties the experiments rely on:

  • Every rule and every solve produces a valid plan that stays clear of maintenance.
  • At a proven optimum, the CP model and the simulator price a plan identically.
  • Rescheduling respects frozen work and the cap on machine changes.
  • The isolated solver process returns the same plan as an in-process solve.
  • The learned run-time estimators rank as experiment 3 reports.

Citation

If you use this code, please cite the article Machine Allocation on a Production Line. CITATION.cff has the details in a machine-readable form, and GitHub offers it as BibTeX or APA under "Cite this repository".

License

Apache License 2.0.

About

Companion code for the article 'Machine Allocation on a Production Line': a CP-SAT model for scheduling unrelated parallel machines with changeovers, release dates and maintenance, compared with dispatching rules in five simulated experiments.

Topics

Resources

Stars

0 stars

Watchers

0 watching

Forks

Releases

Packages

Used by

Contributors

Languages