PLANS.md — Master Implementation Plan

Role: the source of truth for execution — phases, milestones, gates. The Architecture Handbook remains the source of truth for design; this file never restates specifications, it references them. Companion files: MEMORY.md (durable project knowledge), TASKS.md (active backlog).

Maintenance: update this file when a phase starts, completes, or changes scope — in the same PR as the change that caused it.


1. Project Vision (implementation goals)

Implement the Presentation Domain Engine exactly as specified by the handbook: a framework-agnostic, format-agnostic core powering multiple visual-document products without forks. Engineering translation of Vision.md §4's five-year success criteria:

  • The domain model and public command API survive renderer-technology changes without breaking changes (proven by shipping ≥2 renderer families against one frozen contract).
  • Third-party widgets, tools, importers, and exporters register through the same APIs first-party ones use (proven by conformance suites in presentation-testing).
  • Collaboration and AI arrive later as additive layers (proven by keeping their seams — ADR-0002/0005, Command-System.md §14 — untouched and contract-tested throughout).
  • A new engineer reaches productive contribution from documentation alone (proven every time onboarding needs no source-code archaeology).

2. Guiding Principles

  1. Architecture-first. Code that contradicts a boundary table is a bug even when it works. Blocked by the architecture? Take the governance route (Index §11), never a workaround.
  2. Domain-first, inside-out. Build strictly up the dependency graph (ADR-0001's corrected order). A layer starts only when the layer below has passed its quality gate.
  3. Thin vertical slices. Each phase ends with something demonstrable (a milestone), not a pile of untested horizontal plumbing.
  4. Contracts before consumers. Before a layer is built upon, its contract tests live in presentation-testing so every future implementation (including third-party) can verify conformance.
  5. Determinism from day one. Injected IDs/RNG/clock/TextMeasurer in every line of core code — retrofitting determinism is how replay dies.
  6. Test before feature-complete. Property tests for every handbook-stated invariant land with the feature, not after.
  7. Documentation evolves with implementation. Discovering that a spec is wrong produces a governance artifact and a document version bump in the same PR — never a silent divergence between code and handbook.
  8. No heroics. Small PRs, green pnpm check, changesets, honest TASKS.md status. Continuity beats velocity on a multi-year project.

3. Development Phases

Ordering note: this sequence follows the handbook's dependency graph (ADR-0001) and therefore deviates from any intuition that "Runtime" comes early — presentation-runtime is the composition root and depends on events/state/commands (Package-Structure.md §3), so it is built after them. Likewise the rendering core depends on presentation-widget-api, so the widget contract precedes rendering while widget implementations come after it.

Phase 0 — Repository Bootstrap ✅ (done, commit 282831f)

Workspace, tooling, CI, governance surface, 19 placeholder packages with enforced import law. Exit criteria met: pnpm check green end-to-end.

Phase 1 — Domain Layer (presentation-domain)

  • Objectives: the complete domain model as pure types + pure functions.
  • Prerequisites: none (Ring 0).
  • Deliverables: all Domain-Model.md shapes (incl. dataVersion, derived caches as runtime-only); fractional-index ordering utility (Ordering-Strategy.md, injected-RNG jitter); structural validation primitives (Domain-Model.md §12); migration contract shapes (Serialization.md §15's chain pattern); injected-capability interfaces (IdGenerator, Rng, Clock, TextMeasurer shape from ADR-0006); shared ValidationResult/typed-error types.
  • Exit criteria: ordering property tests (fast-check: keys always sort strictly between bounds, never exhaust, deterministic under seeded RNG); validateDocument accepts/rejects the handbook's example documents; zero platform APIs (compile-enforced); package README real.
  • Risks: over-modeling beyond the handbook (scope creep into Theme/Layout territory that is explicitly deferred).

Phase 2 — Event System (presentation-events)

  • Objectives: Emitter/Event/Disposable, taxonomy types, EventOrigin, EventEnvelope, versioned payloads.
  • Prerequisites: Phase 1.
  • Deliverables: Event-System.md §2/§6/§9/§12 contracts; disposal-safety guarantees (§6).
  • Exit criteria: tests prove registration-order delivery, disposal releases all listeners transitively, owner-only emission pattern.
  • Risks: smallest phase — main risk is gold-plating (priority tiers etc. beyond what §10 permits).

Phase 3 — State Management (presentation-state)

  • Objectives: the Store — the system's heart.
  • Prerequisites: Phases 1–2.
  • Deliverables: immutable versioned Store with structural sharing (State-Management.md §2 contract: reference change ⟺ entity written); derived order-cache maintenance (§3); DocumentQuery (§4); write-time ChangeSet tracking → DocumentChangedEvent/RenderStateDiff/ IncrementalSaveOp derivation (§5); dispatch FIFO queue + reentrancy rules (§10); invariant trigger index (§11, for ADR-0003).
  • Exit criteria: property test — random transaction sequences preserve structural-sharing contract; reentrancy tests (nested dispatch queued, cycle depth-limit fails loudly); ChangeSet-derivation is O(writes) (bench baseline recorded).
  • Risks: highest technical risk of the early phases; structural sharing bugs are subtle. Mitigation: exhaustive property tests before Phase 4 starts.

Phase 4 — Command System (presentation-commands)

  • Objectives: the sole mutation pipeline (ADR-0007).
  • Prerequisites: Phase 3.
  • Deliverables: Command contract, Dispatcher, Transaction Manager integration, scoped post-validation (ADR-0003), History Manager (incl. redo invalidation, merge/isNoop), Macro/Batch semantics (Command-System.md §6), Command Factory Registry + payload migration (§16), CommandObserver (§18).
  • Exit criteria: replay property test — serialized command sequences against a snapshot reproduce identical end state under seeded injection (Command-System.md §17); rollback atomicity tests; undo/redo through the full pipeline including undo-fails-validation rollback (§11).
  • Risks: transaction/rollback edge cases; undo state capture memory.

Phase 5 — Runtime (presentation-runtime)

  • Objectives: Engine/DocumentSession composition root.
  • Prerequisites: Phases 1–4.
  • Deliverables: Engine-Lifecycle.md §4 phases (construction, registration, document load sequence §4.3, disposal §4.7); service construction order (§5); Scheduler (merge/defer, §10.3); registry interfaces for Ring 2 (DIP seam, Package-Structure.md §3); multi-session support; EngineConfig capability injection.
  • Exit criteria: Milestone M1 — headless Node process creates an engine, loads the Domain-Model.md §13 example document, dispatches commands, undoes them, disposes cleanly (leak-checked). Two concurrent sessions proven independent (history/selection isolation).
  • Risks: disposal ordering and subscription leaks; this is where Event-System §6's Disposable discipline gets proven or broken.

Phase 6 — Widget Contract (presentation-widget-api)

  • Objectives: the extension contract widgets are written against.
  • Prerequisites: Phase 1 (types); Phase 5 for registry wiring.
  • Deliverables: defineWidget(), WidgetDefinition (incl. hitTest, Widget-System.md §3), Widget Registry (§4 idempotency), RenderNode (homed here per Package-Structure.md 1.1.0), data-migration flow (§10).
  • Exit criteria: widget conformance suite in presentation-testing skeleton form; registration/unregistration mid-session tests (Engine-Lifecycle.md §4.6 degraded-but-safe behavior).
  • Risks: contract churn once real widgets exist — keep 0.x semver honesty until Phase 9 hardens it.

Phase 7 — Rendering Core (presentation-rendering + presentation-renderer-ssr)

  • Objectives: renderer-agnostic projection + first (headless) renderer.
  • Prerequisites: Phases 5–6.
  • Deliverables: canonical RendererAdapter/RendererHandle (ADR-0004), RenderState composition (State-Management.md §6), capability negotiation, widget render lifecycle (Rendering-Architecture.md §10), virtualization hooks (§11); SSR renderer first — headless, deterministic, easiest to test.
  • Exit criteria: Milestone M2 — SSR renderer produces a stable golden-snapshot output for a fixture document; renderer conformance suite exists; unmount/dispose distinction leak-tested.
  • Risks: RenderState recomposition performance; snapshot-test brittleness (mitigate: semantic output snapshots, not pixel).

Phase 8 — Interaction (presentation-interaction)

  • Objectives: Tools, selection/focus/hover, hit-testing, intents.
  • Prerequisites: Phase 7.
  • Deliverables: ToolNode state machine + root-to-leaf dispatch (Selection-and-Interaction.md §2), InteractionState (incl. viewports + preview, §4), Intent Interpreter Registry (§15, ADR-0002), built-in SelectTool/PanTool, geometry hit-testing (§10), gesture preview mechanics (State-Management.md §9).
  • Exit criteria: scripted-input tests: pointer sequences → intents → commands → store state, fully headless; marquee/drag/resize state machines covered; preview never touches the Store (asserted).
  • Risks: the layer with the most historically contradictory spec — re-read ADR-0002 before starting; any ambiguity found goes to governance, not improvisation.

Phase 9 — Widgets Base (presentation-widgets-base) — gated on Text-System.md

  • Objectives: first-party reference widgets: rect, image, group, then text.
  • Prerequisites: Phases 6–8; Text-System.md written and accepted before the text widget starts (ADR-0006, Index §12 — hard gate). rect/group/image may proceed before the gate.
  • Deliverables: four widgets via public contract only; group semantics (Widget-System.md §8); TextMeasurer browser + Node implementations.
  • Exit criteria: every widget passes the conformance suite; the Principle-6 compliance test (Widget-System.md §5) — no core code path exists that these widgets use and a third party couldn't.
  • Risks: text is the hardest problem in the project (cross-renderer fidelity); the document gate exists precisely to force the design first.

Phase 10 — Basic Editor (presentation-renderer-dom + examples/basic-editor)

  • Objectives: first interactive product surface.
  • Prerequisites: Phases 8–9.
  • Deliverables: DOM renderer family; overlay layer (selection, handles, marquee — Rendering-Architecture.md §16); pointer/keyboard normalization; examples/basic-editor becomes a working app.
  • Exit criteria: Milestone M4 — create/select/move/resize/delete/ undo/redo interactively in a browser; e2e infrastructure (Playwright) un-deferred and first tests added.
  • Risks: first place real UX meets the architecture; friction found here feeds governance, not hacks.

Phase 11 — Serialization (presentation-serialization)

  • Objectives: canonical persistence.
  • Prerequisites: Phase 5 (can largely parallel Phases 6–10).
  • Deliverables: envelope + integrity (Serialization.md §2/§10), load sequence with migration chain (§10/§15), quarantine recovery (§11), snapshots (§12), incremental save with removal sets (§13), autosave subscription point (§14).
  • Exit criteria: Milestone M5 — round-trip property test: any valid document serializes → deserializes to deep-equal state (minus derived caches, rebuilt equal); corruption fixtures recover per §10's policy table; migration-chain tests across ≥3 synthetic schema versions.
  • Risks: silent data loss is the nightmare scenario — quarantine tests must include the re-emit-verbatim guarantee (§11).

Phase 12 — Import/Export (presentation-{export,import}-pptx) — gated on Import-Export.md

  • Objectives: first foreign-format adapters.
  • Prerequisites: Phase 11; Import-Export.md written and accepted (Index §12 priority 2) — the mapping tables must exist before code.
  • Deliverables: PPTX exporter (read-only snapshot consumer) and importer (produces PresentationDocument/Import Commands), registered via the Adapter Registry.
  • Exit criteria: Milestone M6 — a fixture deck exports to PPTX that opens in PowerPoint/LibreOffice; import of known-good PPTX fixtures produces valid documents; adapters proven renderer-ignorant (depcruise + type-level).
  • Risks: OOXML fidelity rabbit holes — scope the supported feature matrix in Import-Export.md first, extend iteratively.

Phase 13 — Plugin System (presentation-plugin-api)

  • Objectives: generalized extensibility.
  • Prerequisites: Phases 6–8, 11 (it re-exposes their registries).
  • Deliverables: manifest validation, dependency resolution (topological, cycle-fail — Plugin-System.md §8), lazy activation (§6), permission enforcement (§10), error isolation + rollback of partial contributions (§15), PluginContext.
  • Exit criteria: Milestone M7 — examples/plugin-development loads a real plugin contributing a widget + tool + shortcut; activation-event laziness proven (module not loaded until triggered); a plugin that throws in activate() leaves the system clean.
  • Risks: sandboxed tier stays out of scope (ADR-0005 §1) — resist implementing it "while we're here."

Phase 14 — React Integration (presentation-react)

  • Objectives: first framework binding.
  • Prerequisites: Phase 10.
  • Deliverables: session-scoped hooks (ADR-0004), RenderNode→React reconciler, <PresentationCanvas>; react/react-dom become peer deps.
  • Exit criteria: Milestone M8 — examples/basic-editor variant running on the React binding with identical behavior to the vanilla DOM editor (shared e2e suite passes against both).
  • Risks: the binding staying "thin" (Package-Structure.md §3: no independent logic of substance) — reconciler complexity is the watch item.

Phase 15 — DevTools (presentation-devtools)

  • Objectives: the observability surfaces become an inspector.
  • Prerequisites: Phases 4–5 for observer APIs; Phase 14 for panel UI.
  • Deliverables: event stream + command log panels, provenance filtering ("show me everything plugin X did"), headless observer hooks for CI assertions.
  • Exit criteria: panel runs against the basic editor; read-only contract enforced (no dispatch path importable — depcruise rule).
  • Risks: low; deliberately a community-friendly package.

Phase 16 — Performance Hardening — gated on Performance.md

  • Objectives: budgets, measurement, regression protection.
  • Prerequisites: Phases 1–14 in place; Performance.md written (budgets, methodology, slow-subscriber rule).
  • Deliverables: benchmark suites in tests/benchmarks/ against real subsystems (transaction throughput, ChangeSet derivation, large-document load with partial hydration, renderer diff consumption); CI regression tracking; virtualization + loadPartial exercised at 100s-of-pages scale.
  • Exit criteria: every budget in Performance.md has a benchmark; no per-keystroke path is O(document) (complexity assertions, ADR-0003).
  • Risks: benchmarks lying (fixture documents too small/uniform).

Phase 17 — Collaboration Foundation (checkpoint, not implementation)

  • Objectives: verify the deferred seams still hold before any collab work is committed; write Collaboration.md only when the product need is real (Index §12 priority 6).
  • Prerequisites: Phases 1–16.
  • Deliverables: seam audit (Command-System.md §14, Event-System.md §14, Serialization.md §16, Plugin-System.md §9.6 against the real codebase); Milestone M10 — a demo CollabProviderContribution that replays a recorded op log through ApplyRemoteOperationCommand with zero engine changes.
  • Risks: discovering seam drift late — mitigated by keeping the seam contract tests green from Phase 4 onward.

4. Milestones

# Milestone Phase Proves
M1 Headless engine loads a document, dispatches, undoes, disposes 5 The core loop works with zero UI
M2 SSR renderer produces stable output for a fixture document 7 Projection pipeline + renderer contract
M3 Commands replay deterministically from a serialized log 4 Determinism/replay foundation (collab/AI precondition)
M4 Interactive editing in the browser (basic editor) 10 Full input→intent→command→render loop
M5 Save/load round-trip with migration + corruption recovery 11 Persistence is trustworthy
M6 PPTX export opens in PowerPoint; PPTX import round-trips fixtures 12 The engine meets the outside world
M7 Third-party-style plugin loads lazily and contributes safely 13 Open extension is real, not aspirational
M8 React-bound editor passes the shared e2e suite 14 Framework-agnosticism proven with a second binding
M9 DevTools inspector traces a user action end-to-end 15 Observability contracts pay off
M10 Recorded op log replays through the collab seam, zero engine changes 17 Five-year additive-collaboration bet validated

5. Dependency Graph (phases)

P0 ✅
 └─ P1 Domain
     └─ P2 Events
         └─ P3 State
             └─ P4 Commands ──────────────► M3
                 └─ P5 Runtime ──────────► M1
                     ├─ P6 Widget API
                     │   └─ P7 Rendering Core + SSR ─► M2
                     │       └─ P8 Interaction
                     │           └─ P9 Widgets Base (gate: Text-System.md)
                     │               └─ P10 Basic Editor ─► M4
                     │                   ├─ P14 React ────► M8
                     │                   └─ P15 DevTools ─► M9
                     └─ P11 Serialization ─► M5        (parallel track from P5)
                         └─ P12 PPTX (gate: Import-Export.md) ─► M6
                     P13 Plugins (after P6-P8, P11) ─► M7
 P16 Performance (gate: Performance.md, after P14)
 P17 Collab checkpoint ─► M10

Parallelizable: P11 alongside P6–P10; P13 alongside P10; document-writing gates (Text-System, Import-Export, Performance) alongside preceding phases.

6. Quality Gates (every phase, before the next begins)

  1. pnpm check green (format, md-lint, spell, import law, knip, typecheck, tests, build).
  2. The layer's contract/conformance suite exists in presentation-testing and passes.
  3. Property tests cover every determinism/algebraic invariant the owning handbook document states for the layer.
  4. No new dependency-cruiser exceptions; package dependencies still match Package-Structure.md §3 (or the doc was amended in the same PR).
  5. Package README updated from placeholder to real; changesets recorded.
  6. Zero open governance items against the layer's owning document (no "we'll fix the spec later").
  7. TASKS.md and this file updated (phase status, discovered follow-ups).

7. Definition of Done (per subsystem)

A subsystem is done when:

  • It implements its owning document's contracts verbatim — interface shapes transcribed, not improved; any deviation went through governance and the document was version-bumped.
  • Its boundary table ("what this layer does NOT do") is enforced by tests and/or depcruise rules, not just prose.
  • A conformance suite exists so third-party implementations of its contracts can self-verify.
  • All stated invariants have property tests; error paths from Engine-Lifecycle.md §9's table are exercised.
  • It runs in every environment its Package-Structure.md §8 row claims (universal packages CI-tested in Node; browser packages in the e2e lane once it exists).
  • Its README documents the public surface and links the owning document.
  • Its complexity classes match the handbook's performance statements (O(touch), never O(document), for hot paths).