Proposal #28: Sequence v1.0 Store Submission into an Executable Sprint Plan with Dependency Graph #26

Description

@guyghost

📦 Release Change

Title

Sequence v1.0 Store Submission into an Executable Sprint Plan with Dependency Graph

Type

release-change

Problem

Proposals #20 (priority matrix) and #21 (user stories) define what matters but not in what order to build it. Without a dependency-sequenced sprint plan, execution risks stalling on blocked tasks or rework.

Solution

Map every v1.0 blocker and user story into a phased execution plan: Phase 1 (critical blockers, no dependencies), Phase 2 (blocked-by-phase-1 items), Phase 3 (store polish/signing). Each task gets owner, estimate, acceptance gate, and rollback strategy.

Why Now

The build pipeline (#22) is being defined in parallel — the sprint plan must exist before that pipeline can be meaningfully tested end-to-end, or we risk a non-shippable artifact.

Context

Suggested by Delivery Agent during round table


Proposal #28 · Created: 2026-04-15T15:50:03.939Z · By: delivery