Phase 3 Week 2: Canary Deployment (Aug 8-12, 2026)

Status: PENDING (Scheduled to begin Aug 8)
Timeline: 5 days
Objective: Deploy to 10% production traffic, monitor, obtain decision for progressive rollout


Overview

Canary deployment is a low-risk way to validate production readiness before full rollout. We deploy Phase 2 code to 10% of production traffic and monitor intensively for 2-4 hours.

Success Criteria:

  • Error rate < 0.1%
  • Latency p95 < 100ms
  • Webhook delivery > 99.9%
  • No critical incidents
  • Zero data loss

Rollback Triggers:

  • Error rate > 1% for 5+ minutes → automatic rollback
  • Latency p95 > 500ms for 5+ minutes → automatic rollback
  • Webhook delivery < 99% for 5+ minutes → automatic rollback
  • Any critical incident → immediate rollback

Sunday, Aug 8: Canary Deployment (10% Traffic)

Pre-Deployment (8am-10am)

Checklist:

  • Confirm staging validation complete (all tests passing)
  • Verify team sign-off obtained
  • Confirm rollback plan tested
  • Activate on-call team
  • Notify all stakeholders
  • Open war room channel
  • Start metrics dashboards
  • Brief team on procedure

Communications:

  • Slack: #phase3-deployment - "Canary deployment beginning at 10am"
  • Email: Stakeholders notified
  • War room: https://zoom.internal/c/warroom (open and recording)

Deployment Window (10am-11am)

Step 1: Pre-Deployment Checks (10:00am - 10:05am)

# 1. Verify production API health
curl -s https://api.production.com/health | jq .

# 2. Check database connection
python -c "from app import db; db.session.execute('SELECT 1')"

# 3. Verify all services available
curl -s https://statguardian.production.com/health
curl -s https://pyreverseetl.production.com/health

# 4. Snapshot metrics
aws cloudwatch get-metric-statistics --metric-name CPUUtilization \
  --namespace AWS/EC2 --statistics Average

Step 2: Deploy Code (10:05am - 10:15am)

# 1. Pull latest code
git pull origin main  # Commit 0b73c06

# 2. Run database migrations (if any)
python -m flask db upgrade --tag canary

# 3. Deploy to 10% of servers
# Use load balancer to route 10% traffic to new deployment
# OR use AWS CodeDeploy with deployment group for 10% traffic
./scripts/deploy.sh --version=0b73c06 --traffic=10% --env=production

# 4. Verify deployment
curl -s https://api.production.com/health | jq .version
# Should return "0b73c06"

Step 3: Enable Enhanced Monitoring (10:15am - 10:20am)

# 1. Increase metrics collection frequency (1 second instead of 5)
export METRICS_INTERVAL=1s

# 2. Enable detailed logging
export LOG_LEVEL=DEBUG

# 3. Activate anomaly detection
python scripts/start_anomaly_detection.py

# 4. Open dashboards
# Grafana: https://grafana.production.com (open in separate window)
# Prometheus: https://prometheus.production.com
# Status Page: https://status.example.com (set to "Canary Deployment")

Step 4: Warm Up (10:20am - 10:30am)

  • Verify canary traffic flowing
  • Run synthetic tests
  • Verify no immediate errors
# Run synthetic tests
python scripts/synthetic_tests.py --endpoint=api.production.com \
  --duration=10m --rate=10/sec

Monitoring Phase (10:30am - 2:30pm) - 4 hours

Real-Time Metrics to Watch:

  • Error rate (target: <0.1%)
  • Latency p95 (target: <100ms)
  • Webhook delivery success (target: >99.9%)
  • MCP health status
  • Resource usage (CPU, memory)
  • Request throughput
  • Database connection pool

Monitoring Commands:

# Terminal 1: Error rate monitoring
watch -n 1 'curl -s https://prometheus.production.com/api/v1/query \
  --data-urlencode "query=rate(errors_total[1m])" | jq'

# Terminal 2: Latency monitoring
watch -n 1 'curl -s https://prometheus.production.com/api/v1/query \
  --data-urlencode "query=histogram_quantile(0.95, rate(request_duration_seconds_bucket[1m]))" | jq'

# Terminal 3: Log monitoring
tail -f /var/log/pystreammcp/production.log | grep -E "ERROR|CRITICAL"

# Terminal 4: Grafana dashboard
# Open in browser: https://grafana.production.com/d/canary

# Terminal 5: War room monitoring
# Keep zoom open with screen share of metrics

Hourly Checks (10:30am, 11:30am, 12:30pm, 1:30pm, 2:30pm):

Checkpoint:
├─ Error rate: ___% (threshold: <0.1%)
├─ Latency p95: ___ms (threshold: <100ms)
├─ Webhook success: ___% (threshold: >99.9%)
├─ Memory usage: ___% (looking for leaks)
├─ Database health: OK/DEGRADED
├─ Anomalies detected: YES/NO
├─ Incidents: NONE/[list]
├─ Team assessment: GO/HOLD/ABORT
└─ Next action: Continue/Investigate/Rollback

Action Triggers:

Metric Threshold Action
Error rate > 1% (5+ min) CRITICAL Automatic rollback
Latency p95 > 500ms (5+ min) CRITICAL Automatic rollback
Webhook delivery < 99% (5+ min) CRITICAL Automatic rollback
Memory growing > 5%/min HIGH Investigate memory leak
Database connection pool > 90% HIGH Investigate connection usage
MCP unavailable HIGH Check MCP health, investigate
Unusual error pattern MEDIUM Investigate root cause

Decision Point (2:30pm-3:00pm)

Decision Tree:

Is error rate < 0.1%?
├─ NO → ROLLBACK (automatic already triggered)
└─ YES (continue)
    ├─ Is latency p95 < 100ms?
    │  ├─ NO → INVESTIGATE (likely capacity issue)
    │  └─ YES (continue)
    │      ├─ Is webhook delivery > 99.9%?
    │      │  ├─ NO → ROLLBACK
    │      │  └─ YES (continue)
    │      │      ├─ Are there critical incidents?
    │      │      │  ├─ YES → ROLLBACK or PAUSE
    │      │      │  └─ NO (continue)
    │      │      │      ├─ Is memory stable?
    │      │      │      │  ├─ NO (leaking) → ROLLBACK
    │      │      │      │  └─ YES → SUCCESS
    │      │      │      │
    │      │      │      └─ PROCEED TO PROGRESSIVE ROLLOUT

Sign-Off for Progressive Rollout:

Canary Deployment Sign-Off

Date: Aug 8, 2026
Time: [2:30pm-3:00pm]
Canary Version: 0b73c06
Traffic: 10%

Metrics (4-hour window):
├─ Error rate: [%]
├─ Latency p50: [ms]
├─ Latency p95: [ms]
├─ Latency p99: [ms]
├─ Webhook delivery: [%]
├─ Uptime: [%]
└─ Memory: [stable/leaked]

Incidents: [list or none]

Decision: [✅ GO / ⏸ HOLD / ❌ ROLLBACK]

Approved By:
├─ [x] Engineering Lead (signature)
├─ [x] Operations Lead (signature)
└─ [x] On-Call Primary (signature)

Next Action: [Progressive Rollout Aug 12 / Investigate / Rollback]

Monday-Wednesday, Aug 9-11: Investigation & Holdover

If Canary Goes Well

Aug 9-11: Wait Period

  • Monitor canary metrics continuously
  • Ensure stability maintained
  • Run additional validation tests
  • Prepare for progressive rollout

Aug 12: Decision for 25% Rollout

✅ Metrics stable for 72+ hours?
├─ YES → Proceed to 25% deployment
└─ NO → Continue canary monitoring

If Issues Detected

Investigation Steps:

  1. Identify root cause

  2. Determine if fix needed or investigation only

  3. If fix needed:

    • Implement fix in code
    • Re-test in staging
    • Re-deploy canary
    • Monitor for 2-4 hours
    • Re-evaluate
  4. If investigation only:

    • Document finding
    • Plan mitigation for production
    • Proceed with knowledge

Tuesday, Aug 12: Progressive Rollout Decision

Morning (9am-12pm): Final Review

  • Review 4-day canary metrics
  • Confirm no degradation
  • Verify memory stable
  • Check for any slow issues

Afternoon (1pm-3pm): Decision Meeting

Decision: Should we proceed to 25% rollout?

Analysis:
├─ Canary metrics green? [YES/NO]
├─ Any concerning trends? [list or none]
├─ Team confidence level? [high/medium/low]
├─ Any open issues? [list or none]
└─ Risk assessment? [low/medium/high]

Go/No-Go Vote:
├─ Engineering Lead: [GO/NO-GO]
├─ Operations Lead: [GO/NO-GO]
└─ On-Call Primary: [GO/NO-GO]

Result: [✅ PROCEED / ⏸ HOLD / ❌ ROLLBACK]

If GO: Proceed to Week 2, Day 3


Rollback Procedures

Automatic Rollback (Triggered by Metrics)

When error rate > 1% for 5+ minutes:

# 1. Immediately triggered (automated)
./scripts/rollback.sh --version=previous --traffic=100% --env=production

# 2. Verify rollback successful
curl -s https://api.production.com/health | jq .version
# Should return previous version hash

# 3. Monitor metrics
# Watch error rate drop back below 0.1%
# Watch latency return to baseline

# 4. Notify team
# Slack: #phase3-deployment - "Automatic rollback triggered. Version: [old] → [new]"
# War room: Post incident details

Manual Rollback (If Issues Detected)

# 1. Stop canary traffic
./scripts/deploy.sh --stop --version=0b73c06

# 2. Revert to previous version
./scripts/deploy.sh --version=previous --traffic=100%

# 3. Verify rollback
curl -s https://api.production.com/health | jq .

# 4. Investigate issue
# Create incident report
# Root cause analysis
# Plan remediation

# 5. Communicate
# Status update to stakeholders
# Reschedule canary for when issue is fixed

Post-Rollback Actions

  1. Immediate (first hour)

    • Verify rollback successful
    • Monitor metrics return to baseline
    • Notify stakeholders
    • Stop enhanced monitoring
  2. Short-term (next day)

    • Root cause analysis
    • Fix identified issue in code
    • Re-test fix in staging
    • Plan new canary attempt
  3. Communication

    • Send incident summary
    • Document lessons learned
    • Schedule follow-up

Incident Response During Canary

If Critical Issue Detected

Escalation:

1. Alert triggered → On-call responds (immediate)
2. Incident severity assessed → Escalate if critical
3. War room opened → Team assembles
4. Root cause identified → Fix or rollback decided
5. Action taken → Rollback or fix deployed
6. Monitoring → Verify resolution

Critical Issue Examples:

  • Data corruption detected
  • Security breach found
  • Production API down
  • Massive performance degradation
  • Webhook delivery < 95%
  • Complete MCP unavailability
  • Database connection exhaustion

Response:

  1. Page on-call immediately
  2. Open war room
  3. Assess severity
  4. Make rollback decision (usually immediate for critical)
  5. Execute rollback
  6. Post-incident review

Success Metrics for Week 2

Canary Success

  • ✅ 4-hour monitoring completed
  • ✅ Error rate < 0.1% throughout
  • ✅ Latency p95 < 100ms throughout
  • ✅ Webhook delivery > 99.9% throughout
  • ✅ No critical incidents
  • ✅ Memory stable (no leaks)
  • ✅ Proceed to progressive rollout approved

Decision Criteria Met

  • ✅ Metrics confirm production readiness
  • ✅ Team confidence high
  • ✅ Zero show-stoppers identified
  • ✅ Rollback plan verified working (if needed)
  • ✅ Monitoring infrastructure validated

Next Phase: Progressive Rollout (Aug 12-15)

Upon successful canary sign-off:

  • Aug 12 (Tue): 25% rollout
  • Aug 13 (Wed): 50% rollout
  • Aug 13 (Wed): 100% rollout
  • Aug 14-15 (Thu-Fri): 24-hour monitoring

Phase 3 Week 2 Status: PENDING (Aug 8-12)
Previous: Phase 3 Week 1 (Aug 2-7)
Next: Phase 3 Week 2-3 Progressive Rollout (Aug 12-15)